Short answer: a three-way match means you pay a supplier only after three documents agree: the purchase order (what you agreed to buy, at what rate), the goods receipt note or GRN (what actually reached the site, in what condition), and the supplier invoice (what you are being asked to pay). If quantity, rate or tax differ between them, the bill is held until someone explains the difference. For Indian construction firms, the GRN does a second job too: under the GST law, input tax credit is available only once goods have actually been received.[1]
Most contractors already have all three documents. The problem is that they live in three places: the PO with purchase, the GRN in a register at the site store, and the invoice in accounts. The match happens late, by email, or not at all.
Why it matters more on a construction site
A factory receives goods at one gate. A contractor receives cement, steel, aggregates, electrical items and hired equipment at several sites, often in part loads, often unloaded after office hours. That creates a few common gaps:
- Short or part deliveries. Six of eight truckloads of aggregate arrive, but the invoice is for the full PO quantity.
- Rate drift. The invoice uses a newer price list than the rate agreed in the PO.
- Wrong site. Material ordered for Site A is delivered to Site B, so the GRN and the cost code do not line up.
- Rejected material. Damaged or below-spec items are sent back, but the invoice is not reduced.
- Duplicate bills. The same delivery is billed twice, once against the delivery challan and once against the tax invoice.
Each gap is small on its own. Over a year of procurement across several sites, they add up to real money and a budget that no longer matches the BOQ. (If you are still separating cost control from scheduling, our post on BOQ vs WBS for site measurements and cost control explains how the two fit together.)
What each document proves
| Document | Who creates it | What it proves | Check against |
|---|---|---|---|
| Purchase order (PO) | Purchase / project team | What you agreed to buy: item, specification, quantity, rate, tax, delivery site, payment terms | BOQ line or budget cost code |
| Goods receipt note (GRN) | Site store keeper or engineer | What actually arrived: quantity accepted, quantity rejected, date, condition, vehicle and challan number | PO quantity and specification |
| Supplier invoice | Supplier | What you are being asked to pay: quantity billed, rate, GST, total | PO rate and GRN accepted quantity |
A payment-tracking product's documentation describes the GRN in the same way: a record raised against the PO to confirm that the delivery arrived in the expected quantity and condition, so that payment follows what was actually delivered.[2]
The GST angle: receipt is a condition for input tax credit
Section 16(2) of the CGST Act lists the conditions a registered buyer must meet before taking input tax credit (ITC). In plain terms, the buyer needs:[1]
- a tax invoice or debit note from a registered supplier;
- the supplier to have reported that invoice in its outward supply statement, so it is communicated to the buyer;
- actual receipt of the goods or services (goods delivered to another person on the buyer's direction count as received);
- the tax to have been paid to the government by the supplier; and
- the buyer's own return to have been filed.
Two provisos in the same section are directly relevant to site procurement:[1]
- Goods in lots. When goods on one invoice arrive in lots or instalments, credit is available only when the last lot is received. A GRN for every load is how you know when that happened.
- 180-day payment rule. If the buyer does not pay the supplier the value plus tax within 180 days of the invoice date, an amount equal to the credit taken has to be paid back with interest. Credit can be taken again once the supplier is paid.
There is also an outer time limit: ITC for an invoice cannot be taken after 30 November following the end of the financial year, or after the annual return is filed, whichever is earlier.[1]
So the GRN is not just a store-room formality. It is the record your accounts team relies on when it claims credit, and it is often the first thing a reviewer asks for. This is general information, not tax advice; confirm treatment of specific cases with your chartered accountant.
How to run a three-way match: step by step
1. Raise every purchase on a PO. Include item code and specification, quantity, unit, rate, GST rate, delivery site and the BOQ line or cost code it is charged to. Emergency purchases still get a PO, raised the same day.
2. Share the PO with the site. The store keeper should see what is expected before the truck arrives. Without the PO in hand, the GRN just copies the challan.
3. Record a GRN for every delivery, including part loads. Count or measure what arrived. Record quantity accepted and quantity rejected separately, with a reason for each rejection. Note the challan or e-way bill number and vehicle number. Attach a photo of the challan.
4. Book the invoice against the PO and its GRNs. Accounts should not enter a supplier bill without picking the PO it belongs to and the GRNs it covers.
5. Compare line by line. For each item: invoice quantity against total accepted GRN quantity, invoice rate against PO rate, and invoice GST against the PO tax rate.
6. Apply a tolerance you have agreed in writing. Bulk materials such as sand and aggregate are rarely delivered to the exact cubic metre. Decide in advance how much quantity or rounding difference is acceptable, and hold anything outside it.
7. Resolve exceptions with a named owner. Short delivery: ask for a credit note or a revised invoice. Rate difference: ask for the PO rate or approve a PO amendment. Rejected goods: record the return and expect a credit note.
8. Approve and schedule payment. Only matched invoices go to the payment run. Track the invoice date so you pay within the agreed terms and well inside the 180-day GST window.
9. Close the PO. When the full quantity is received and billed, close it so no further invoice can be booked against it.
Checklist: before a supplier bill is paid
- ☐ PO exists and is approved, and charged to the right site and cost code
- ☐ Every delivery on the invoice has a GRN
- ☐ Invoice quantity ≤ total accepted GRN quantity
- ☐ Invoice rate = PO rate (or an approved PO amendment exists)
- ☐ GST rate and supplier GSTIN are correct on the invoice
- ☐ Rejected quantities are excluded or covered by a credit note
- ☐ Invoice is not a duplicate (same supplier, number and amount)
- ☐ For goods in lots, the last lot's GRN date is recorded
- ☐ Payment date is planned within terms and the 180-day window
Common mistakes to avoid
- Back-dating GRNs when the invoice arrives. The GRN should be made on the day goods arrive. A GRN created from the invoice proves nothing.
- One GRN for a week of deliveries. You lose the trail for part loads and rejected items.
- Matching only the total. A bill can total correctly while one item is short and another is over-billed.
- No link to the budget. If the PO is not tied to a cost code, a matched invoice can still blow the budget unnoticed.
- Keeping the challan photo on someone's phone. Attach it to the GRN record.
Where software helps
You can run a three-way match on paper or spreadsheets if volumes are low. It gets hard when several sites, many suppliers and part deliveries are involved, because the three documents are kept by different people.
Woxox Construction OS covers requisitions, RFQ, purchase orders and GRNs alongside budgets and cost codes and site records, so the site and the purchase team work from the same PO. Woxox Finance keeps double-entry books, GST invoicing and returns, approvals and an audit trail. The point is simple: when the PO, GRN and bill sit in one system, the comparison takes minutes instead of a chain of emails.
See it on your own procurement workflow: talk to Woxox.
FAQs
What is the difference between two-way and three-way matching? A two-way match compares only the PO and the invoice. A three-way match adds the GRN, so you also confirm the goods actually arrived in the quantity billed. For physical materials on site, the three-way match is the safer default.
Is a delivery challan the same as a GRN? No. The challan is the supplier's document that travels with the goods. The GRN is your own record of what you accepted after checking the delivery. The GRN usually refers to the challan number.
Can we take GST input tax credit before the goods reach the site? Generally no. Section 16(2) of the CGST Act makes receipt of goods a condition for credit, though goods delivered to another person on your direction count as received. For goods on one invoice delivered in lots, credit is available on receipt of the last lot.[1]
What should we do when the invoice quantity is more than the GRN quantity? Hold the invoice, tell the supplier, and pay only for the accepted quantity once you have a credit note or revised invoice. Do not adjust the GRN to match the bill.
Does three-way matching apply to services and subcontract work? The idea is the same, but the "receipt" is a certified measurement or work completion record instead of a GRN. For subcontractors that usually means a measured, certified bill against the work order.
What happens if we pay a supplier late? Apart from the commercial terms, under the CGST Act, if you do not pay the value plus tax within 180 days of the invoice date, an amount equal to the credit taken must be paid back with interest; credit can be taken again after payment.[1]
By WOXOX Editorial Team
Sources
- Central Board of Indirect Taxes and Customs, CGST Act, 2017, Section 16: Eligibility and conditions for taking input tax credit (including the explanation on deemed receipt, the provisos on lots and on payment within 180 days, and sub-section (4)). https://taxinformation.cbic.gov.in/content/html/tax_repository/gst/acts/2017_CGST_act/active/chapter5/section16_v1.00.html