Short answer: A running account (RA) bill is an interim bill for work done and measured so far on a contract. Calculate it cumulatively: take the up-to-date measured quantity of each BOQ item, multiply by the contract rate, subtract what was already billed in earlier RA bills, then apply the deductions your contract and the law require (retention, advance recoveries, materials issued, taxes). Every quantity on the bill should point back to a signed entry in the measurement book.
RA bills are where a project's money actually moves, and also where most contractor–client arguments start. This guide walks through the format, a worked calculation, the usual deductions, and a checklist you can use before a bill leaves the site office.
What an RA bill is (and is not)
An RA bill is a part payment against the contract while work is in progress. It is not the final settlement. Public-works rules treat these as "on account" payments that are adjusted in the final bill, which is why the cumulative method matters: each RA bill restates the whole job to date, so an error in one bill can be corrected in the next.
The quantities come from measurements of work actually done, usually recorded jointly by the engineer and the contractor. Government departments in India follow detailed procedures for this. The CPWD Works Manual has separate sections on measurement of work, test checking of measurements, and the time schedule for paying bills, and it now provides for electronic measurement books through the PFMS portal.[1] A port authority's published SOP, for example, asks for joint measurement, measurement book entries in the first week of the following month, and certification of measurements within five working days.[2] Private contracts are usually less formal, but the same logic protects both sides.
How a quantity is measured (deductions for openings, laps, how earthwork is taken) should follow the method of measurement named in the contract. In India that is often IS 1200, the Bureau of Indian Standards' series on methods of measurement of building and civil engineering works.[3]
The standard RA bill format
Formats differ by client, but almost every RA bill has the same parts:
- Header: contract or work order number, name of work, contractor, RA bill number (RA-1, RA-2 …), period covered, date of measurement, measurement book reference.
- Abstract of quantities and amounts: one row per BOQ item with these columns:
- Item number and description (exactly as in the BOQ)
- Unit and contract rate
- BOQ (tendered) quantity
- Quantity up to the previous bill
- Quantity in this bill
- Quantity up to date (cumulative)
- Amount up to date, amount up to previous bill, amount for this bill
- Extra and deviation items: any approved extra item or quantity beyond the BOQ, with its approval reference. Keep these separate from regular items.
- Gross value summary: total up to date, less total up to previous bill, equals gross value of this bill.
- Deductions and recoveries: retention or security deposit, advance recoveries, materials issued by the client, statutory deductions, penalties if any.
- Net payable and the sign-off block: prepared by, checked by, measurements verified by, approved for payment by.
How to calculate an RA bill: a worked example
In an item rate contract you are paid for the measured quantity at the contract rate; in a percentage rate contract the tendered percentage above or below the estimate is applied to the gross bill.[4] The figures below are illustrative only. Rates and percentages come from your own contract.
| BOQ item | Unit | Rate (₹) | Up to previous | This bill | Up to date | Amount up to date (₹) | Amount this bill (₹) |
|---|---|---|---|---|---|---|---|
| Excavation in ordinary soil | m³ | 180 | 800 | 400 | 1,200 | 2,16,000 | 72,000 |
| PCC M15 below footings | m³ | 5,200 | 60 | 35 | 95 | 4,94,000 | 1,82,000 |
| RCC M25 in slabs | m³ | 7,800 | 0 | 40 | 40 | 3,12,000 | 3,12,000 |
| Total | 10,22,000 | 5,66,000 |
Step by step:
- Up-to-date value. Multiply each cumulative quantity by its rate and add them: ₹10,22,000.
- Less value up to the previous bill. Earlier bills covered 800 m³ excavation and 60 m³ PCC: ₹1,44,000 + ₹3,12,000 = ₹4,56,000.
- Gross value of this bill. ₹10,22,000 − ₹4,56,000 = ₹5,66,000. This should equal the "this bill" column, which is a useful cross-check.
- Contractual deductions. Suppose the contract says 5% retention and recovery of the mobilisation advance at 10% of each bill's gross value: retention ₹28,300, advance recovery ₹56,600. That leaves ₹4,81,100 before statutory items.
- Statutory items. Add or deduct GST, income-tax TDS, GST TDS (for notified government buyers) and any labour welfare cess as the law and your contract require. Rates and thresholds change, so take them from your accountant, not from last year's bill.
- Net payable. The amount the client pays after all of the above.
Why cumulative rather than "this period only"? If RA-2 over-measured PCC by 5 m³ and RA-3 corrects the up-to-date quantity, the error disappears automatically. A bill built only from "this period" quantities carries mistakes forward.
Deductions and recoveries to expect
| Deduction | Where it comes from | What to check |
|---|---|---|
| Retention / security deposit | Contract conditions | Percentage, cap, and when it is released |
| Mobilisation or machinery advance recovery | Contract conditions | Recovery rate, start bill, interest if any |
| Secured advance on materials | Contract conditions | Recovered when the material is used in work |
| Materials issued by client (steel, cement) | Issue register | Quantity issued vs theoretical consumption |
| Income-tax TDS, GST TDS, labour cess | Law in force on the bill date | Current rate, threshold, who deducts |
| Liquidated damages / penalties | Contract conditions and notices | Written basis and approval |
A recovery that is not in the contract, or that has no document behind it, is the start of a dispute. Write the clause number beside each deduction.
Where RA bills go wrong
- No joint measurement. The contractor's quantities and the engineer's quantities were taken on different days with different assumptions.
- Description drift. The bill says "RCC slab" but the BOQ item is "RCC M25 in slabs and beams up to floor five level". Copy BOQ descriptions exactly.
- Quantities above BOQ without approval. Cumulative quantity crosses the tendered quantity and nobody flags it until audit.
- Part rates without a record. Some contracts allow part payment for unfinished items. Note the reason and the balance due, or the next bill will double-count.
- Deductions from memory. Advance recovery or materials issued are taken from last month's bill rather than the register.
- Measurements not tied to cost codes. The bill gets paid, but the project team still cannot say whether the slab is over budget. Our BOQ vs WBS guide covers how to link measured quantities to cost control.
Pre-submission checklist
Before an RA bill leaves the site office:
- ☐ Every quantity has a measurement book page or e-MB reference
- ☐ Measurements were taken jointly or the contractor was notified in writing
- ☐ Item descriptions, units and rates match the BOQ exactly
- ☐ "Up to previous" equals "up to date" from the last approved bill
- ☐ Items above BOQ quantity are flagged with an approval reference
- ☐ Extra items are listed separately with approval and rate analysis
- ☐ Each deduction has a contract clause or register reference
- ☐ Statutory rates were checked against current law, not copied
- ☐ Prepared, checked and approved signatures are in place
- ☐ The cumulative total reconciles with the project's cost report
Keeping measurements, BOQ and bills in one place
Most of the checks above fail for one reason: the BOQ sits in one spreadsheet, the measurements in a register or another sheet, and the bill is typed again from both. Woxox Construction OS keeps the WBS, BOQ, work packages and measurements, and budgets and cost codes together, so the quantities an RA bill needs are already in one place. GST invoicing and the books run in Woxox Finance on the same database.
If you want to see your own BOQ and measurement flow set up this way, book a walkthrough.
FAQs
What is the full form of RA bill? RA stands for running account. An RA bill is an interim bill raised during the contract for work done and measured so far, adjusted later in the final bill.
How often is an RA bill raised? As often as the contract allows, commonly monthly or at agreed milestones. Some public bodies set a monthly cycle with fixed days for measurement, certification and payment.
What is the difference between an RA bill and a final bill? RA bills are part payments while work continues. The final bill settles the whole contract after completion: final measured quantities, all extras and deviations, and release or adjustment of retention.
Why is the RA bill calculated on cumulative quantities? Because each bill restates all work done to date. Paying "up to date minus up to previous" corrects earlier errors automatically and keeps the running total auditable.
Can an RA bill include quantities above the BOQ? Only with approval as the contract allows (a deviation or extra item order). Show them separately with the approval reference so they are not paid as regular items by mistake.
Which taxes apply to an RA bill? It depends on the contract and the client: GST on the contractor's invoice, income-tax TDS by the payer, and GST TDS where the buyer is a notified government entity. Confirm current rates with your accountant before each bill.
By WOXOX Editorial Team
Sources
- Central Public Works Department, CPWD Works Manual 2019 (contents: 5.12 Measurement of Work, 5.14 Test Checking of Measurements, 5.18.1 Time Schedule for Payment of Bills; salient features on e-MB through PFMS). Copy hosted by NDMC: https://www.ndmc.gov.in/departments/Departments/Finance/nodal_cell/CPWD Works Manual 2019.pdf
- New Mangalore Port Authority, SOP for processing contractors' bills: https://newmangaloreport.gov.in/sites/default/files/2021-06/SOPContractors bill.pdf
- Bureau of Indian Standards, IS 1200 (methods of measurement of building and civil engineering works), e.g. Part 1 Earthwork: https://archive.org/details/gov.in.is.1200.1.1992
- Finance Department, Government of Tripura, Manual for Procurement of Works 2020 (item rate and percentage rate contracts; payment for measured quantity): https://finance.tripura.gov.in/sites/default/files/Manual-for-Procurement-of-Works-2020 -Repaired.pdf