Subcontractor Bills in Construction: Work Orders, Certification and Deductions

How main contractors in India should issue work orders, certify subcontractor bills and apply TDS, retention and recoveries before releasing payment.

In this article
  1. 1. Start with the work order, not the bill
  2. 2. Measure from site, not from the subcontractor's sheet
  3. 3. Certify in a fixed sequence
  4. 4. Apply deductions in a fixed order
  5. 5. TDS on subcontractor payments: what the Income Tax Department says
  6. 6. Pay on time, especially to small subcontractors
  7. 7. Close out properly: the final bill
  8. Subcontractor bill checklist
  9. Common mistakes
  10. Where software helps
  11. FAQs
  12. Sources

Short answer: a subcontractor bill should be paid only against a signed work order, quantities your own site team has measured and certified, and rates from that work order. Before release, the certified amount passes through a fixed list of deductions: TDS, retention, recovery of advances, cost of material you issued, and any documented back-charges. Each deduction must trace back to a clause in the work order or a statutory rule. If any line can't be traced, the bill isn't ready.

Most main contractors already know how to bill their client. The subcontractor side gets less care. It runs on WhatsApp photos, handwritten measurement sheets and a running balance someone keeps in Excel. That's where margin leaks: paying for the same quantity twice, forgetting to recover the cement you issued, or releasing retention before the defects period ends.

This guide covers the subcontractor (or "petty contractor" / labour contractor) side. Billing your own client through running account bills is a separate process with its own format. We cover it in our RA bill guide.

This is general information, not tax or legal advice. Check statutory treatment for your firm with your chartered accountant.

1. Start with the work order, not the bill

Every dispute over a subcontractor bill is really a dispute over the work order. Before a single bill comes in, the work order (WO) should fix:

Work order item Why it matters at billing time
Scope, linked to your BOQ items Stops bills for work that was never awarded
Unit of measurement and rate per item Avoids "per sq ft vs per running metre" arguments
Labour-only or labour-plus-material Decides whether you recover material cost and how TDS is worked out
Material you will issue free or chargeable, with wastage allowance Basis for material recovery
Mobilisation or other advance, and how it is recovered Basis for advance recovery per bill
Retention % and release condition Basis for retention deduction and later release
Billing cycle and certification time Sets expectations; avoids "bill pending with PM" for weeks
Back-charge clause: notice, chance to fix, then deduct Back-charges without notice are the most disputed deduction
Payment terms Feeds your payables plan

Keep one WO per subcontractor per scope. If scope changes, issue an amendment or extra-item order. Don't just approve a higher quantity on the bill.

2. Measure from site, not from the subcontractor's sheet

The subcontractor's bill is a claim. Your measurement is the evidence. The site engineer should record quantities for the billing period against the same BOQ items and units used in the WO, ideally on the same measurement sheets or measurement book used for your client billing.

Three checks catch most errors:

  1. Cumulative, not period-only. Record the total quantity to date, then subtract the quantity already paid. Period-only bills hide double counting.
  2. Same item, same unit. If your client pays you per cubic metre of concrete, measure the subcontractor in cubic metres too, so you can compare cost and revenue on the same item.
  3. Work done, not work started. Partly finished items should follow a stage rule written into the WO (for example, 60% on shuttering and reinforcement, balance on casting), not a guess.

3. Certify in a fixed sequence

A clean certification chain looks like this:

  1. Site engineer checks quantities against measurements and marks rejected or deferred items.
  2. QS or billing engineer applies WO rates, checks cumulative quantities against the BOQ, and lists the deductions.
  3. Project manager approves the certified value and any back-charges.
  4. Accounts checks PAN, GST details on the subcontractor's invoice and TDS, books the bill and schedules payment.

The certified bill (not the subcontractor's original claim) is what accounts should book. Keep both. The difference between "claimed" and "certified" is your record of what was rejected and why.

4. Apply deductions in a fixed order

Use the same order on every bill so anyone can audit it:

Step Line Basis
A Gross value of work done to date Cumulative certified quantity × WO rate
B Less: value certified in earlier bills Previous bill register
C Value of this bill (A − B)
D Less: retention WO % on C, held until the release condition
E Less: advance recovery WO recovery % or fixed instalment
F Less: material issued (chargeable) and excess wastage Site issue register vs WO wastage allowance
G Less: back-charges Only with notice and a record under the WO clause
H Add: GST, if the subcontractor is registered and charges it Subcontractor's tax invoice
I Less: TDS See below
J Net payable

Keep a running balance per subcontractor for retention held, advance outstanding and material issued. Each bill should reduce or add to these balances, so the final bill is a reconciliation, not a negotiation.

5. TDS on subcontractor payments: what the Income Tax Department says

From tax year 2026-27, TDS on payments to contractors and sub-contractors sits under Section 393(1) of the Income-tax Act, 2025, Table S. No. 6(i). It replaces the old Section 194C. The Income Tax Department's TDS FAQs and the section text give these figures:[1][2]

  • Rate: 1% where the contractor is an individual or HUF; 2% for others.
  • Threshold: no deduction if a single payment does not exceed ₹30,000 and the total paid to that contractor in the year does not exceed ₹1,00,000. Cross either limit and TDS applies.
  • Scope: covers payment for carrying out any work, including supply of labour for carrying out any work.
  • Transport contractors: no deduction for a contractor in the goods-carriage business who owns ten or fewer goods carriages and gives a declaration with PAN, subject to the payer reporting the prescribed details.[2]

Two practical points for site teams:

  • Collect the subcontractor's PAN before the first bill, not at year-end. Without it, deduction rates are much higher.
  • Your accounts team should decide, with your CA, which base value TDS is worked out on (for example, how GST shown separately on the invoice is treated) and apply it the same way on every bill.

6. Pay on time, especially to small subcontractors

Many labour and specialist subcontractors are registered micro or small enterprises. Under the MSMED Act, 2006, a buyer who doesn't pay a micro or small enterprise within 45 days of accepting the goods or services is liable for compound interest on the delay.[3] Slow certification doesn't stop that clock from mattering. Set a target number of days from bill receipt to certification, and track it.

7. Close out properly: the final bill

The final bill should settle every running balance:

  • Final measured quantities against the WO and all amendments
  • Advance fully recovered
  • Material issued reconciled against consumption and wastage allowance
  • Back-charges settled, each with its supporting record
  • Retention: amount held and release date per the WO
  • No-dues confirmation from the subcontractor, including labour payments and statutory dues where your contract requires it

Subcontractor bill checklist

  • ☐ Signed work order (and amendments) on file
  • ☐ Bill items match WO items and units
  • ☐ Quantities measured by your site team, cumulative to date
  • ☐ Previous bills subtracted; no item paid twice
  • ☐ Rejected or deferred items listed with reasons
  • ☐ Retention deducted at the WO %
  • ☐ Advance recovery applied
  • ☐ Chargeable material and excess wastage recovered
  • ☐ Back-charges backed by notice and records
  • ☐ PAN on file; TDS worked out per current rules
  • ☐ GST invoice checked if GST is charged
  • ☐ Certified by site, QS and PM before accounts books it
  • ☐ Running balances (retention, advance, material) updated

Common mistakes

  • Paying on the subcontractor's measurement. It becomes the only record when disputes start.
  • Not recovering issued material. Cement, steel and consumables issued from your store are easy to forget unless every issue is logged against the subcontractor.
  • Back-charges without notice. A deduction with no prior notice and no chance to fix is the one most likely to be disputed.
  • Releasing retention by habit. Retention should be released on the WO condition, such as completion of the defects period, not when someone asks.
  • No link to the budget. If subcontractor bills aren't booked against the same cost code as the BOQ item, you can't see margin by item until the project is over.

Where software helps

On a single small site, a well-kept register and a spreadsheet can work. On several sites with dozens of work orders, the problem is keeping measurements, budgets, purchase records and bills connected.

Woxox Construction OS keeps BOQ, work packages and measurements, budgets and cost codes, requisitions, purchase orders and GRNs, and site records on one platform. The quantities your site team measures and the cost they draw against sit in the same place your billing team works from.

See it on your own work orders and BOQ: talk to Woxox.

FAQs

What is a work order in construction? A work order is the main contractor's written award of a defined scope to a subcontractor. It sets items, units, rates, advances, retention, material terms and payment terms. Every subcontractor bill should be checked against it.

Who should certify a subcontractor bill? Normally the site engineer checks quantities, the QS or billing engineer applies rates and deductions, and the project manager approves. Accounts then checks tax details and books the certified value.

What is the TDS rate on payments to a sub-contractor in 2026-27? Under Section 393(1), Table S. No. 6(i) of the Income-tax Act, 2025: 1% for an individual or HUF and 2% for others. It applies when a single payment exceeds ₹30,000 or the year's total exceeds ₹1,00,000.[1]

Is retention deducted from subcontractor bills? Only if the work order says so. When it does, deduct the agreed percentage on each bill and release it on the agreed condition, usually after the defects period.

Can a main contractor deduct back-charges from a subcontractor bill? If the work order allows it, yes. It works best with written notice, a chance for the subcontractor to fix the problem, and a record of the cost. Take legal advice on specific disputes.

How is a subcontractor bill different from an RA bill? An RA bill is what you raise on your client for work done. A subcontractor bill is what your subcontractor raises on you. Both should use the same BOQ items and measurements so cost and revenue can be compared item by item.


By WOXOX Editorial Team

Sources

  1. Income Tax Department, Government of India, FAQs on Tax Deducted at Source (TDS): rates and thresholds for payments to contractors and sub-contractors under Section 393(1), Table S. No. 6(i). https://www.incometaxindia.gov.in/documents/d/guest/faqs-on-tax-deducted-source
  2. Income Tax Department, Government of India, Income-tax Act, 2025, Section 393: Tax to be deducted at source (Table S. No. 6(i) and Section 393(4), S. No. 8). https://www.incometaxindia.gov.in/w/section-393-6
  3. Office of the Development Commissioner (MSME), Government of India, Delayed Payments to Micro and Small Enterprises under the MSMED Act, 2006. https://www.dcmsme.gov.in/publications/LegalFramework.pdf