Short answer: retention money is a part of each running (RA) bill that the client keeps back as security until the contractor has finished the work and fixed any defects. Your contract decides the rate, the ceiling, when it is released and whether you can swap it for a bank guarantee. For a contractor, the important part is the tracking: every deduction on every bill should go into a retention ledger, so that on the release date you can show exactly how much is held, on which bills, and what the client still owes you.
This guide explains how retention usually works in Indian construction contracts, how to calculate the deduction, a ledger format you can copy, and the release checklist that gets the money back on time. It follows on from our guide to linking BOQ, WBS and site measurements to cost control.
This is general information, not legal or tax advice. Read your own contract, and ask your adviser how retention is treated for GST and TDS in your case.
What retention money is (and what it is called)
Contracts use different names for the same idea: retention, retention money, security deposit (SD) or withheld amount. In each case the client deducts a percentage of the gross bill value and keeps it for a set period. It gives the client a fund to fall back on if the contractor walks away, leaves work incomplete or does not fix defects.
Retention is different from the performance guarantee, although the two often appear in the same clause:
| Performance guarantee | Retention / security deposit | |
|---|---|---|
| How it is given | Up front, usually as a bank guarantee, FDR or surety bond | Deducted from each running bill (sometimes allowed up front instead) |
| When it is given | Shortly after the work is awarded | Builds up bill by bill |
| What it protects | Proper performance of the contract | Completion and defects during the defect liability period |
| Typical release | After completion, as the contract states | After completion and the defect liability period, as the contract states |
How government contracts set it: two published examples
Government contract forms are a useful reference because they are published. Two examples:
- CPWD General Conditions of Contract 2023. The general rules ask the contractor for a performance guarantee at the percentage in the contract schedule, and a security deposit equal to 2.5% of the tendered amount, collected by deductions from the running bills and the final bill.[1]
- EPC General Conditions of Contract, IIT Hyderabad (April 2026). Clause 1A allows the client to deduct 2.5% of the gross amount of each running and final bill until the deposit reaches 2.5% of the tendered value. The deposit can also be given up front as an FDR or bank guarantee from a scheduled bank, and deductions can be released against a bank guarantee once they build up to a minimum of ₹5 lakh.[2] The same document returns the performance guarantee after the completion certificate is recorded, with proportionate rules for part completion.[2]
Private contracts vary widely. Some use a higher rate, some release half on completion and half after the defect liability period, and some allow a retention bond. The rate, ceiling, release trigger and substitution rights in your contract are the only ones that matter for your project.
How to calculate the retention deduction on an RA bill
Retention is normally a percentage of the gross value of work done in that bill, before other deductions. Check your contract: some apply it to the cumulative value, some exclude price-variation or material advances.
A simple worked example (illustrative numbers):
- Contract value (tendered amount): ₹2,00,00,000
- Retention: 2.5% of each bill, capped at 2.5% of contract value = ₹5,00,000
- RA bill 04 gross value of work this bill: ₹18,00,000
- Retention this bill: 2.5% × ₹18,00,000 = ₹45,000
- Retention held before this bill: ₹3,90,000
- Retention held after this bill: ₹4,35,000 (still under the ₹5,00,000 cap)
Once the cap is reached, later bills should show zero retention. This is one of the most common errors: deductions carry on after the ceiling because nobody tracks the running total.
Steps for each bill:
- Take the gross value of work certified in this bill (from your measurements).
- Apply the retention rate from the contract.
- Check the running total against the ceiling. Deduct only up to the cap.
- Record the bill number, date, gross value, retention deducted and running total in the retention ledger.
- Match the client's payment advice against your figure. Any difference gets raised the same week.
For how measurements turn into a bill in the first place, see the Construction OS page.
A retention ledger you can copy
Keep one ledger per contract (and per subcontract, if you also deduct retention from your own subcontractors).
| Bill no. | Bill date | Gross value this bill | Rate | Retention this bill | Running total held | Cap | Paid date | Client figure | Difference |
|---|---|---|---|---|---|---|---|---|---|
| RA-01 | 2.5% | ₹5,00,000 | |||||||
| RA-02 | 2.5% | ₹5,00,000 | |||||||
| … | |||||||||
| Final |
Add a header block with the information you will need on the release date:
- Contract number, client, project and contract value
- Retention clause number, rate, ceiling and release terms
- Whether a bank guarantee can replace retention, and the minimum amount
- Completion date (actual), completion certificate reference
- Defect liability period start and end dates
- Open defects list reference
Two rules keep the ledger reliable: fill it from the same bill data your accounts team posts (never re-typed later), and reconcile it with the client's payment advices every month.
Releasing retention: the checklist
Retention can sit unpaid simply because the release date passes and nobody writes to the client. A short routine prevents that.
60 days before the defect liability period ends
- ☐ Confirm the end date from the completion certificate and the contract clause.
- ☐ Pull the open defects list and assign each item an owner and a closing date.
- ☐ Check whether any bank guarantee given in place of retention needs extending or will be returned.
30 days before
- ☐ Close the open defects and keep photos, dates and the client's sign-off for each.
- ☐ Reconcile the retention ledger with the client's records.
On the release date
- ☐ Send a written release request quoting the contract clause, the ledger total and the defects close-out record.
- ☐ Attach the ledger and the completion certificate.
After the request
- ☐ Diary a follow-up for 15 days later.
- ☐ Record the amount and date received; close the ledger.
Run the same checklist in reverse for subcontractors: if you hold their retention, release it on the terms you agreed. Paying it late damages the relationship you will need on the next job.
Common mistakes
- Deducting past the cap. Without a running total, retention continues after the ceiling is reached.
- Mixing retention with other deductions. Retention, mobilisation advance recovery, material recovery and penalties each need their own line, or reconciliation becomes guesswork.
- No clear defect liability start date. If nobody records the completion certificate date, nobody knows when the clock ends.
- Ignoring bank-guarantee substitution. Where the contract allows it, releasing accumulated retention against a bank guarantee can free up working capital earlier. Weigh the guarantee's cost first.
- Forgetting subcontract retention. A main contractor can be owed retention by the client and owe retention to subcontractors at the same time. Track both.
Where software helps
On one project a spreadsheet works. Across several sites, each with its own bills, rates and dates, the ledger needs to come straight from the bills themselves. Woxox Construction OS keeps BOQ, work packages and measurements, budgets and cost codes, purchase orders and site records on one platform, so the figures behind each bill come from the same place your team already works in.
To see how your own billing and retention tracking would look, book a Woxox demo.
FAQs
What is retention money in construction? A part of each running bill that the client keeps back as security until the work is complete and defects have been fixed. It is also called a security deposit or withheld amount.
How much retention is deducted from a running bill? Whatever your contract says. As one published example, CPWD's General Conditions of Contract 2023 set the security deposit at 2.5% of the tendered amount, collected through deductions from the running and final bills.[1]
Is retention money the same as a performance guarantee? No. A performance guarantee is usually given up front as a bank guarantee or similar instrument. Retention builds up from deductions on each bill. Many contracts ask for both.
When is retention money released? On the trigger in your contract, usually linked to completion and the end of the defect liability period. Some contracts release part on completion and the rest later.
Can retention be replaced by a bank guarantee? Some contracts allow it. The April 2026 EPC conditions published by IIT Hyderabad, for example, let deductions be released against a scheduled bank's guarantee once they build up to at least ₹5 lakh.[2]
How should a contractor track retention across projects? Keep one ledger per contract with bill number, gross value, rate, retention deducted, running total, cap and payment date, filled from the same bill data your accounts team uses and reconciled monthly.
By WOXOX Editorial Team
Sources
- Central Public Works Department, Office Memorandum No. DG/CON/Misc./30 dated 22 Sep 2023, "General Conditions of Contract 2023 – Construction Works", General Rules and Directions, Rule 11 (copy published in an IIT Kanpur tender, accessed 5 Nov 2026): https://iitk.ac.in/iwd/file/2025/12-AC-EE-2025/GCC2023.pdf
- Indian Institute of Technology Hyderabad, "General Conditions of Contract (GCC) for EPC Projects", April 2026, Clauses 1 and 1A (accessed 5 Nov 2026): https://www.iith.ac.in/assets/files/tenders/General_Conditions_of_Contract_GCC_for_EPC_Projects_2026.pdf