Modular Kitchen and Interior Quotation Format: What to Include So Clients Approve Faster

A clear interior and modular kitchen quotation format: the sections, line items, specs, exclusions and payment terms that help clients say yes sooner.

In this article
  1. Why vague quotes slow approvals down
  2. The quotation format, section by section
  3. 1. Header
  4. 2. Scope summary
  5. 3. Room-by-room or zone-by-zone line items
  6. 4. Materials and specification schedule
  7. 5. Services
  8. 6. Exclusions
  9. 7. Price summary and taxes
  10. 8. Payment terms
  11. 9. Timeline, warranty and change orders
  12. 10. Acceptance
  13. A modular kitchen example layout
  14. Pre-send checklist
  15. Where software helps
  16. FAQs
  17. Sources

Short answer: a quotation gets approved faster when the client can check it without phoning you. That means one section per room or kitchen zone, a line for each unit with its size and quantity, the material and hardware specified by grade and brand (not "as per design"), a clear list of what is excluded, GST shown separately, a validity date, and payment milestones tied to work stages. Vague lines such as "kitchen work – lump sum" or "electrical as required" are the ones clients question, renegotiate or compare unfairly with a cheaper quote.

This guide gives you a section-by-section format, a modular kitchen example layout, a pre-send checklist and the wording that heads off the most common disputes. It is about the document you send the client. How you build the estimate behind it is a separate job.

Why vague quotes slow approvals down

A client comparing three interior quotes is trying to answer one question: am I getting the same thing for less, or less for less? If your quote doesn't let them answer that, they ask for a meeting, they ask a friend, or they go with the lowest number.

One large interior company's consumer guide tells homeowners to look in a quote for the brands, grades and finishes of plywood, laminates and hardware, the quantities, the services covered, and what is excluded, such as loose furniture, appliances, false ceilings or civil work.[1] Your clients are being told what to look for. A quote that already answers those points saves a round of questions.

Clear quotes help you too:

  • Fewer scope arguments later. If the quote says "hinges: soft-close, brand X, 2 per shutter", there is nothing to argue about at handover.
  • Faster internal handoff. The production team and site supervisor work from the same lines the client approved.
  • Cleaner change orders. When the client asks for an extra loft or a different shutter finish, you can price the difference line by line.

The quotation format, section by section

Use this order. It moves from "who and what" to "how much" to "on what terms", which is the order most clients read in.

1. Header

  • Your business name, address, GSTIN (if registered), phone and email
  • Quotation number and date
  • Client name, site address and contact
  • Project name (for example "3BHK, Tower B, Flat 1204: kitchen and two bedrooms")
  • Validity: "This quotation is valid until ." Material prices move; a validity date protects you and tells the client when to decide.
  • Version: "Rev 2, replaces Rev 1 dated ." Clients often hold several versions. Make it obvious which one is current.

2. Scope summary

Three to six lines in plain language: which rooms, what is being made or installed, and what the client is handling themselves. For example: "Modular kitchen (L-shape) with loft, two wardrobes, TV unit, false ceiling in living room. Client supplies appliances and loose furniture."

3. Room-by-room or zone-by-zone line items

This is the core of the quote. For each room or kitchen zone, list every unit on its own line with:

Column What to write Example
Item Unit name and location Base unit below hob, 900 mm
Size Width × height × depth, or running metres / square feet 900 × 720 × 560 mm
Specification Carcass, shutter, finish, edge band 18 mm plywood carcass, laminate shutter, matching edge band
Hardware Type, brand, quantity Soft-close hinges × 2; tandem drawer × 1
Qty Number of units 1
Rate Per unit or per square foot, as you price it (your rate)
Amount Qty × rate (calculated)

Keep the same unit of measure within a section. Don't mix "per sq ft" and "lump sum" for similar units in one room. That is exactly what makes clients suspicious.

4. Materials and specification schedule

Put the detailed spec in one schedule instead of repeating it on every line:

  • Board: material, thickness and grade. Where the board is made to an Indian Standard, name it the way the supplier's sheet does. IS 303, for example, is the BIS standard for general-purpose plywood and covers MR and BWR grades.[2]
  • Shutter and finish: laminate, acrylic, membrane, veneer, paint; gloss or matt; edge banding.
  • Hardware: hinges, drawer channels, baskets, lift-up systems, handles. Give the brand or say "brand X or equivalent, approved by client".
  • Countertop: material, thickness, edge profile, sink and hob cut-outs.
  • Accessories: tall unit fittings, corner solutions, cutlery trays.

If you offer good / better / best options, show them as separate columns in this schedule, not as three different quotes.

5. Services

List what labour and services are included: design and drawings (and how many revisions), site measurement, carpentry, installation, electrical points, plumbing points, painting, debris removal, cleaning before handover. The same consumer guide warns homeowners to ask whether installation, site supervision, debris removal, transport and revisions are charged separately.[1] Answer that question in the quote itself.

6. Exclusions

Many disputes start here. Write a short, specific list:

  • Appliances (hob, chimney, built-in oven) unless listed above
  • Civil work: wall breaking, tiling, plumbing re-routing
  • Loose furniture and soft furnishings
  • Society or building permissions and their charges
  • Anything not described in sections 3 to 5

"Anything not listed is excluded" is useful, but only as the last line, after the specific items.

7. Price summary and taxes

Sub-total by room, then the project sub-total, any discount shown as its own line, then GST, then the grand total. Show GST as a separate line with the rate you will charge, so the client knows whether a figure is before or after tax. The GST rate and classification for furniture, fit-outs and works contracts depend on how the supply is structured, so confirm yours with your accountant before you send the quote.

A quotation is not a tax invoice, but it helps to collect at the quote stage the details your invoice will need later. Under Rule 46 of the CGST Rules, a tax invoice must carry, among other things, the recipient's name and address (and GSTIN if registered), the HSN or SAC code, a description, quantity, taxable value, tax rate and amount, and the place of supply.[3] If the quote already has them, the invoice is quicker to make and less likely to contain mistakes.

8. Payment terms

Tie each payment to a stage the client can see, not to a date alone. A typical structure has a booking amount, a payment on design sign-off, one when materials are ordered or dispatched, one after installation, and a final amount at handover after the snag list is closed. Write the percentage for each stage and what "done" means for that stage.

9. Timeline, warranty and change orders

  • Timeline: design sign-off to installation, with the client's dependencies (for example, "site ready and appliances available by ").
  • Warranty: what is covered, for how long and by whom (your work vs manufacturer warranties on hardware).
  • Changes: "Any change after design sign-off will be quoted as a change order and needs written approval before work starts."

10. Acceptance

A line for the client's signature and date, or a sentence saying that written acceptance by email or message confirms the order. Keep the signed version with the project.

A modular kitchen example layout

Here is how the kitchen section of a quote can look. The figures are left blank on purpose. Use your own rates.

Zone Item Size (mm) Spec ref. Qty Amount
Base Sink unit with bottle pull-out 900 S1, H2 1
Base Hob unit with 3 drawers 900 S1, H3 1
Base Corner unit with corner solution 900 × 900 S1, H4 1
Wall Wall units with lift-up shutter 1800 run S2, H5 1
Tall Tall unit with pantry fittings 600 S1, H6 1
Loft Loft shutters 2400 run S2 1
Top Countertop with sink and hob cut-outs 3000 run C1 1
Services Installation, plumbing and electrical points as per drawing – – 1

"S1", "H2" and "C1" point to the materials schedule (section 4), so the specification is written once and every line stays short.

Pre-send checklist

Run this before any quote leaves the studio:

  • ☐ Quotation number, date, validity date and revision number are on page one
  • ☐ Every line has a size and quantity; no "lump sum" for anything that can be measured
  • ☐ Board, finish and hardware are specified by grade and brand (or "or equivalent, client to approve")
  • ☐ Number of design revisions included is stated
  • ☐ Exclusions list is specific
  • ☐ GST is a separate line and the rate has been checked
  • ☐ Payment milestones are tied to visible stages
  • ☐ Change-order wording is included
  • ☐ Totals add up (recalculate once, by someone other than the person who made it)
  • ☐ The file name and PDF match the revision number

Where software helps

A quote is easier to keep accurate when it comes from the same record as the project. If the rooms, units and BOQ already live in your project, the quote is a view of that data rather than a separate spreadsheet. When the client approves, the same lines can become purchase and production orders without re-typing. We described that flow, from first enquiry to handover, in our guide to interior design studio software.

WOXOX Interior Design OS brings the sales pipeline, projects and rooms, a BOQ estimator, purchase orders, production orders, punch lists and client and vendor portals into one workspace. See it on your workflows: book a demo.

FAQs

What is the difference between a quotation and a BOQ in interior work? A BOQ (bill of quantities) is the measured list of items and quantities used to build the estimate. The quotation is the client-facing document built from it, with specifications, exclusions, taxes, payment terms and validity added.

Should I quote a modular kitchen per square foot or per unit? Either works if you are consistent and the client can see what each figure covers. Per-unit pricing with sizes is usually easier for clients to compare, because it shows what they get for each part of the kitchen.

How long should an interior quotation be valid? There is no fixed rule. Pick a period that matches how often your material prices change, write the date on the first page, and re-issue a new revision if it lapses.

Do I have to show GST separately on a quotation? A quotation is not a tax invoice, but showing GST as its own line avoids the most common confusion about whether a figure includes tax. Confirm the rate and classification with your accountant.

What should go in the exclusions section? Anything a client might reasonably assume is included but is not: appliances, civil work, loose furniture, building permissions and their charges, and extra design revisions beyond the number stated.

How do I handle changes after the client approves the quote? Issue a written change order that lists the added or removed lines, the price difference and any effect on the timeline, and get it approved before the work starts.


By WOXOX Editorial Team

Sources

  1. Design Cafe, "What's Really in Your Interior Quote? A Guide to Transparent Home Interior Pricing", 10 Aug 2026. https://www.designcafe.com/blog/home-interiors/transparent-home-interior-pricing/