Short answer: build an interior design BOQ (bill of quantities) room by room, with every line carrying an item description, specification, quantity, unit, rate and amount. Price each line from material plus labour plus a stated wastage allowance, add your margin openly, and get the client to sign off a frozen version. Then raise purchase orders from that signed BOQ, grouped by vendor, so every rupee you spend can be traced back to a line the client approved. Margin most often leaks in the gap between "estimate approved" and "materials ordered".
This guide is about the estimate itself: how to structure it, price it, freeze it and turn it into orders. If you want the bigger picture of running a studio from first enquiry to handover, read our interior design studio software guide.
Why room-by-room beats one long list
Clients think in rooms: "what does the kitchen cost?" Site teams work in rooms too: the carpenter finishes the master bedroom wardrobe before moving on. A BOQ arranged by room matches both.
It also makes changes easier. When a client drops the study unit or upgrades the living-room ceiling, you revise one section and the difference is visible, instead of hunting through a 300-line sheet.
The usual structure is three levels:
- Room or zone (living, kitchen, master bedroom, common areas).
- Work category inside the room (civil and demolition, false ceiling, flooring, carpentry and modular units, painting and polishing, electrical, plumbing, soft furnishings, loose furniture).
- Line item (for example, "wardrobe carcass, 18 mm plywood, laminate outside, liner inside").
Keep a short "general" section for items that belong to the whole project, such as site protection, debris removal and final cleaning, so they don't get forgotten or double-counted across rooms.
What every BOQ line should carry
A line that only says "Wardrobe – ₹1,20,000" will be argued over. A line that can be checked will not.
| Column | What to write | Why it matters |
|---|---|---|
| Item code | Room + category + number (e.g. MBR-CP-03) | Lets you trace POs, site records and changes back to one line |
| Description | What it is, in plain words | The client must recognise it |
| Specification | Material, thickness, finish, brand or "equivalent", hardware type | Stops silent downgrades and "that's not what we agreed" |
| Quantity | Measured from drawings or site | The number you'll be held to |
| Unit | sq ft / sq m, running ft / m, nos, lump sum | Different trades measure differently; say which |
| Rate | Per unit, with or without tax stated | Makes comparison and revision possible |
| Amount | Quantity × rate | The only column clients usually read |
| Remarks | Exclusions, assumptions, client-supplied items | Where future disputes are settled |
On units: be consistent and write down how you measure. India's standard for this is IS 1200, the Bureau of Indian Standards series on methods of measurement for building works. It has separate parts for ceilings and linings, floor finishes, painting and polishing, woodwork and joinery, glazing and plumbing, among others.[1] You don't need to follow it clause by clause for a residential project, but using it as your reference means your quantities can be defended if a client or their consultant checks them.
Step by step: from drawings to a priced BOQ
1. Measure from drawings, then verify on site
Take quantities off your approved layout and elevation drawings first. Then do a site check before you price: wall lengths, ceiling heights, window positions and existing services rarely match the builder's plan exactly. Record site measurements against the room and line they affect.
2. Split each item into material and labour
For each line, price material and labour separately even if you show one rate to the client. Carpentry, for example, is board and laminate (material), hardware (material) and fabrication and installation (labour). When a vendor's price moves, you know which part of the rate changed.
3. Add wastage as a stated allowance
Boards are cut, tiles break, paint is lost in rollers. Put a wastage allowance on material lines and write the percentage in your internal sheet, so it is a decision rather than a guess. Base it on your own past jobs: compare what you ordered with what the BOQ said on the last few projects.
4. Price, then add margin openly
Build the cost rate first (material + wastage + labour), then add your margin or design fee as a separate, consistent layer. Studios that bury margin inside random line rates find it hard to revise estimates without either losing money or looking inconsistent.
5. Handle tax deliberately
How GST applies depends on what you are supplying. Under GST law, a works contract covers construction, fit-out and similar work on immovable property that involves transferring goods, and it is treated as a supply of services; the general rate for works contract services under heading 9954 is 18%, with some lower-rate categories.[2] Loose furniture or products you simply sell may be a supply of goods with their own rate. Decide with your chartered accountant how your contracts are classified, and show on the BOQ whether rates include or exclude tax.
6. Freeze a version at sign-off
When the client approves, save that BOQ as a numbered version with the date and the client's approval. Don't keep editing the same file. Every later change becomes a variation: a new line or a revised line, with its own quantity, rate and approval.
Worked example (illustrative)
The figures below are made up to show the arithmetic. They are not market rates.
| Code | Item | Qty | Unit | Cost rate (₹) | Margin | Client rate (₹) | Amount (₹) |
|---|---|---|---|---|---|---|---|
| MBR-CP-01 | Wardrobe, 18 mm ply, laminate finish, soft-close hinges | 60 | sq ft | 1,500 | 20% | 1,800 | 1,08,000 |
| MBR-FC-01 | Gypsum false ceiling with cove | 140 | sq ft | 100 | 20% | 120 | 16,800 |
| MBR-PT-01 | Emulsion paint, two coats on putty | 420 | sq ft | 25 | 20% | 30 | 12,600 |
| Master bedroom subtotal | 1,37,400 |
The cost rate for the wardrobe already includes board and laminate with wastage, hardware and labour. If the hinge spec changes from soft-close to standard, you revise one input and the line recalculates; the client sees exactly which line moved and by how much.
From signed BOQ to purchase orders
This is where most studios lose money. The BOQ is approved, then purchasing happens over WhatsApp from memory. A few weeks later nobody can say why laminate spend is 15 sheets over.
A simple discipline fixes most of it:
- Group BOQ lines by vendor. All laminate lines across rooms go to the laminate supplier; all hardware lines go to the hardware supplier. One PO per vendor per order cycle.
- Every PO line points to a BOQ line. Quantity on the PO can't exceed BOQ quantity plus the stated wastage without someone approving it.
- Production orders for the workshop. If you fabricate in-house or through a factory, issue a production order per unit (wardrobe, kitchen base units) with the drawing and the BOQ code, so the workshop builds what was sold.
- Receive against the PO. When material arrives, check it against the PO, not against memory. Short or wrong deliveries get noted the same day.
- Compare actual to estimate per line. Once a room is done, compare what was ordered and spent with the BOQ. That comparison is what makes your next estimate's wastage and rates more accurate.
If you work on larger fit-outs with a main contractor, the same idea applies at bigger scale; our guide on BOQ vs WBS and tying site measurements to cost control covers how measurements link to cost codes.
Checklist before you send an estimate
- ☐ Arranged by room, with a general section for whole-project items
- ☐ Every line has a specification, not just a name
- ☐ Units stated, and measured the same way across rooms
- ☐ Site measurements checked against drawing quantities
- ☐ Material, labour and wastage split in your internal sheet
- ☐ Margin applied consistently, not hidden in odd rates
- ☐ Tax treatment decided and shown (inclusive or exclusive)
- ☐ Exclusions and client-supplied items written in remarks
- ☐ Version number and date on the sheet
- ☐ Plan for how variations will be approved and priced
How Woxox fits
Interior Design OS keeps this in one place: your pipeline, projects broken into rooms, a BOQ estimator, purchase orders, production orders, punch lists, and client and vendor portals. The estimate, the orders raised from it and the site punch list sit on the same project record, so you can see whether what you bought matches what the client approved. It is an add-on to the Woxox Professional or Business plan.
FAQ
What is a BOQ in interior design? A bill of quantities lists every item of work and material for a project, with quantity, unit, rate and amount. In interior design it is usually arranged room by room and becomes the basis for the client contract, purchasing and billing.
How is an interior BOQ different from a quotation? A quotation may be a single total or a short list. A BOQ breaks the work into measurable lines with specifications, so both sides can check quantities, compare rates and price changes line by line.
What units are used in an interior design BOQ? Commonly square feet or square metres for ceilings, flooring, painting and panelled carpentry; running feet or metres for skirting, cornices and countertops; numbers for fixtures and hardware; and lump sum for small items. State the unit on every line and measure consistently. IS 1200 is the Indian reference for measurement methods.
How much wastage should I add? There is no single correct figure. Use your own past projects: compare material ordered with BOQ quantities by category and set a percentage for each. Write it down so it can be reviewed.
How do I handle changes after the client signs? Freeze the signed BOQ as a version. Treat every change as a variation with its own line, quantity, rate and client approval, and update purchasing only after approval.
Is GST on interior work always 18%? Not necessarily. Fit-out work on immovable property is generally treated as a works contract service, where the general rate is 18%, but the classification depends on your contract and what you supply. Confirm with your chartered accountant.
Turn your next estimate into orders that match it
See how a room-by-room BOQ becomes purchase orders and production orders on one project record. Book a Woxox demo.
By WOXOX Editorial Team
Sources
- Bureau of Indian Standards, IS 1200 "Method of measurement of building and civil engineering works", list of parts (CED 44), via the public mirror at https://law.resource.org/pub/in/bis/manifest.ced.44.html. Current editions are listed on BIS "Know Your Standards": https://www.services.bis.gov.in/
- GST Council, "Works Contract Services" (explainer on the definition, Schedule II para 6(a), SAC 9954 rates and Notification No. 03/2022-Central Tax (Rate)): https://gstcouncil.gov.in/sites/default/files/2024-04/workscontractservices_pra.pdf